NEW QUESTION 23
Which risk management perspective is concerned with a programme's interdependencies with other initiatives?
- A. Strategic
- B. Programme
- C. Project
- D. Operational
Answer: A
NEW QUESTION 24
Which is a feature of an effective programme organization?
- A. A quality assured configuration management system
- B. Clear accountability for each management role
- C. A business case agreed by the stakeholders
- D. Monitored and controlled programme changes
Answer: D
NEW QUESTION 25
What type of programme may also be referred to as a 'must do' programme?
- A. Emergent
- B. Compliance
- C. Vision-led
- D. Portfolio
Answer: B
NEW QUESTION 26
Which response pays a third party to accept a risk?
- A. Avoid
- B. Prepare contingent plans
- C. Accept
- D. Transfer
Answer: D
NEW QUESTION 27
Which role provides a home for governance and control?
- A. Programme board
- B. Programme office
- C. Programme assurance
- D. Sponsoring group
Answer: B
NEW QUESTION 28
What document provides terms of reference for the Sponsoring Group?
- A. Resource Management Plan
- B. Programme Brief
- C. Organization Structure
- D. Quality and Assurance Strategy
Answer: C
NEW QUESTION 29
Which area of management within programme quality tracks and protects project outputs?
- A. Asset
- B. Process
- C. Information
- D. Supply chain
Answer: A
NEW QUESTION 30
Which governance theme includes carrying out an assessment of the effectiveness of the decisions taken by programme leaders?
- A. Quality and Assurance Management
- B. Leadership and Stakeholder Engagement
- C. Blueprint Design and Delivery
- D. Programme Organization
Answer: B
NEW QUESTION 31
Which is NOT a governance theme?
- A. Vision
- B. Blueprint design and delivery
- C. The business case
- D. Benefit profile
Answer: D
NEW QUESTION 32
Which is NOT a characteristic of the programme management principles?
- A. They are valid in all programme management contexts
- B. They enable practitioners to achieve transformational change
- C. They ensure practitioners follow common procedures
- D. They have been successful when applied in practice
Answer: A
NEW QUESTION 33
What programme role is MOST likely to also have a role within a project board to represent the interests of the business?
- A. Programme Board
- B. Programme Manager
- C. Business Change Manager
- D. Programme Office
Answer: A
NEW QUESTION 34
Which is a description of a programme resource?
- A. A process to control a programme
- B. A logical grouping of projects within a programme
- C. The objective of a programme
- D. An input required by a programme
Answer: D
NEW QUESTION 35
Which role is MOST likely to have a focus on managing the costs of training operational teams during transition?
- A. Senior Responsible Owner
- B. Programme Office
- C. Programme Manager
- D. Business Change Manager
Answer: B
NEW QUESTION 36
Which is NOT a purpose of a Blueprint?
- A. Describe how to get to the future state
- B. Provide a usable basis for designing the Projects Dossier
- C. Ensure coherence of the entire future state
- D. Provide a basis for modelling benefits
Answer: A
NEW QUESTION 37
Under which heading in the POTI model should the current performance level of an operational area be recorded?
- A. Technology
- B. Process
- C. Organization
- D. Information
Answer: B
NEW QUESTION 38
Which describes an impact of a risk?
- A. Possibility that something will go wrong
- B. The amount of risk that will be tolerated
- C. An event that might increase a programme's outcome
- D. Effect on the programme if something goes wrong
Answer: D
NEW QUESTION 39
Which is the BEST description of the purpose of the Projects Dossier?
- A. Describes the context when starting up projects
- B. Provides detailed requirements for each project
- C. Specifies a thorough brief for starting each project
- D. Lists the projects involved in the delivery of the Blueprint
Answer: D
Explanation:
Projects dossier provides a list of projects required to deliver the blueprint, with high-level information and estimates.
NEW QUESTION 40
Which role is responsible for delivering the capability?
- A. Programme board
- B. Business change manager
- C. Programme manager
- D. Senior responsible owner
Answer: D
NEW QUESTION 41
What term represents the desired state of the organization achieved after transition?
- A. Output
- B. Benefit
- C. Outcome
- D. Capability
Answer: C
NEW QUESTION 42
Which activity requires the programme office to be independent of the initiatives?
- A. Project guidance
- B. Administrative duties
- C. Control of standards
- D. Project support
Answer: A
NEW QUESTION 43
......
MSP Foundation MSP-Foundation Dumps - Secret To Pass in First Attempt: https://pass4sure.examstorrent.com/MSP-Foundation-exam-dumps-torrent.html